Isilon upgrade
Scheduled Maintenance Report for CU Boulder RC
Completed
The Isilon upgrade has completed successfully. We observed no interruption to the service.
Posted Jan 28, 2020 - 14:49 MST
Update
We are beginning this update now. This operation should be non-disruptive.
Posted Jan 28, 2020 - 12:15 MST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 28, 2020 - 12:00 MST
Scheduled
We will be upgrading the Isilon cluster at this time. It will be a rolling upgrade which should result in no downtime. There may be brief lags in performance as each node completes it's upgrade and resets itself.
Posted Jan 27, 2020 - 12:55 MST
This scheduled maintenance affected: Research Computing Core.