Planned Maintenance for HPCF UPS

Scheduled Maintenance Report for CU Boulder RC

Completed

Today's UPS planned maintenance has concluded successfully with no outage for Summit or Blanca.
Posted Oct 02, 2019 - 13:42 MDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 02, 2019 - 09:00 MDT

Scheduled

Next week on our regular planned maintenance day the CU Boulder datacenter team will be conducting planned maintenance on the UPS that supports Summit and Blanca HPC in the HPCF. No outages are expected, and jobs will continue to be scheduled and run as normal.

While the UPS is under maintenance both Summit and Blanca HPC will be running on bypass power. Bypass power carries increased risk of disruption from instabilities in our utility power supply.
Posted Sep 27, 2019 - 10:34 MDT
This scheduled maintenance affected: Blanca.